Construction is scheduled to start in March, 2012 and be complete by Memorial Day Weekend.
Please visit the Richmond MORE Website or Join the Richmond-MORE Email List to find out when and how you can help in the construction of the skills area.
We're seeking financial donations to help cover the cost of materials and expert advice from IMBA's Trail Solutions and Apline Trails. We still need to raise $28,000 in order to complete this project! Click here to donate!
Any questions? Email: info@richmond-more.org for more information.
Construction Timeline 2012
While there are still some finishing touches left to complete, the Skills Area is OPEN and ready to ride!
March 31 - April 14 | Site Prep - Brush Clearing, etc. |
April 21 - April 28 | Mechanized Work - Starting Hills Construction, etc. (no volunteers needed) |
May 5 & 6 | Skills Area Construction |
May 12 & 13 | Skills Area Construction |
May 19 | Finish Work |
May 26 | Opening |
July 4 | Ribbon Cutting |